1

Saudi Electricity Company

  • Construction of 132kV Double Circuit OHL from S/S 8068(Huraymala) to S/S 8502(HawatSudair)
  • Including Change Order on 380 KV Line

2

Saudi Aramco

(MRK)

  • Replacement of 13.8 KV Line in GOSP 7 & Construction of 115 KV Overhead Transmission Line for GOSP 1,4,5,7,8 – Saudi Aramco

3

Bisha Cement Plant

  • Fabrication and Installation of vent duct for bag filter truss conveyor and structural steel fabrication and erection work.
  • Fabrication and installation of structural steel for bucket convoyer
  • Local fabrication and installation or preheat tower and raw mill
  • Installation of blower, fan motors A/C, Water Chiller pumps, plant utility works.
  • Hydro-Pneumatic Reservoirs and pipeline works
  • Pipeline works for fire fighting, fuel, air, lubrication, water treatment plant and jacketing works.
  • Installation of laboratory equipment & electric equipments, pumps sewage plant utility works

4

Saudi Electricity Company

  • Construction of 132kV Double Circuit OHL from S/S 9009(PP9) to S/S 8505(Rumah)

5

S.S.E.M

  • Installation of 10 MW Power plant a Khalibar
  • Fabrication and Installation of OIL, Diesel and water pumps and associated pipe lines
  • Fabrication and installation of overhead crane, Ventilation System with Intake air filter
  • Construction of water Treatment facility and treated water tank (Elevated with structure)
  • Electrical works (Cabling Switch gear, transformer and control panel)
  • Installation of Exhaust Stack

6

Lucky Development Co. Ltd.

  • Installation of Water chiller, Chilled Water Pipe Line
  • Fabrication and installation of HVAC Duct works & Ventilation
  • Installation of smoke and
  • pressuraization Fans

7

SSEM

  • Foundation and Tower Erection for 132 KV Double Circuit Overhead Line from Al-Wajh To Al- Ulla

8

Swayeh

  • 13.8kV Distribution network for water conveyance project from Busayath well field to Qurayat city

9

SCECO PP5

  • Rehabilitation of Air Intake Hood
  • Fabrication and Installation of Lube Oil Condenser
  • Major repair of Transition Duct

10

Olayan Saudi Holding Co.

  • Renovation works for irrigation water line for lanscaping
  • Fabrication and Installation of water tower, Pumps for Oil, Water and Diesel fuel
  • Fabrication and Installation of Auxiliary Water tank and associated Civil work

11

E.A. Juffali & Brothers

  • Installation of Water Chiller and Piping
  • Duct works & Ventilation and related facilities

 

12

Arab investment Co.

  • Installation of Electric meters
  • Fabrication and Installation of Electric Main Panel

13

Muncipality of Hofuf

  • Installation of Water Treatment Tank and Aeration Tank
  • Rehabilitation of Sludge Pump (250 Hp) and major rehabilitation of Scraper facility
  • Fabrication of water tower structure (30 meter hieght)

14

G.I.D. Training Center

  • Installation of Generator sets and Overhead Crane
  • Pipe Works for Fuel, oil, water radiator etc.

15

SCECO PP5

  • Exhaust Diffuser and silencer
  • Fabrication and Installation of Flycol cooler
  • ABB Gas Turbine works and Pumps for Lube Oil, Air/Air cooler

16

SCECO PP3

  • Installation of Starting Package for 60 MW Turbine
  • Repair of Exhaust Stack Structure with sheet Metal Cladding (Internal and External)
  • Repair of Transition Duct

17

Olayan Saudi Holding Co.

  • Construction of Multi-purpose Hall with electric facilities, fire alarm, fire fighting & pipe works.

18

Gurayat Government Hospital

  • Mechanical work for HVAC, Ducting and Installation of air Handling Units and Related Equipment
  • Mechanical Work for HVAC
  • Testing and Balancing

19

Saudi Aramco Riyadh Bulk Plant Catch Basin

  • Installation of Riyadh Bulk Plant
  • Pipe works and installation of works for Catch Basin
  • Water treatment Rehabilitation Works

20

Saudi Aramco Sullayil

  • Fabrication and Installation of Heat Exchanger
  • Associated works for Heat Exchanger
  • Fabrication and Installation of Air/air and Oil Cooler

21

Six Villas at Sulaimania, Riyadh

  • Renovation, HVAC, Plumping and Electrical works and Civil works

22

Rafha Power Station

  • Installation of 12 Mw Generator, Fuel, Oil and fire Fighting Pipe Works
  • Installation of Water Treatment Plant

23

Saudi Aramco, Riyadh

  •  
  • Fabrication and Installation of Structural Works

24

Electricity Coorporation, Turaif

  • Renovation and Retrofit Works 13.8 KV switchgear and control panel

25

Electricity Coorporation

  •  
  • Installation of 6 MW Generator and Switchboard
  • Electrical Installation (Transfomer, Switch Gear control panel, etc.)

 

26

 

Electricity Coorporation, Mahad al Dahab

  • Complete Installation and Operation of 3×3.5 MW Diesel Power Plant
  • Mechanical Works at the Power Plant

27

Electricity Coorporation, Tabuk

  • Installation of 33 KV, 630A Switchgear
  • Testing and Commissioning of Switchgear

28

G.I.D Training Center

  • Installation of 2 MW Transformer
  • Testing & Commissioning of Transformer and Switchgear

29

Electricity Coorporation, Khakir

  • Mechanical Installation & fabrication works for 3×1.75 MW diesel Power Plant installation
  • Water Treatment Plant Rehabilitation

30

SCECO PP3

  • Repair of Stack joint Seals
  • Rehabilitation of Starting Package

31

Al Janoub Project

  • Hydrogen Storage Bottle and Building Structure
  • 5 x 1,360 KVA with Switchboard & fuel oil treatment
  • Supply & Installation of Crude Oil Generator and Heavy Fuel Oil Treatment Plant
  • Supply & Installation of Water Treatment facility
  • Installation of Distribution Panel

32

SCECO PP4

  • Repair and Installation of Exhaust Stack & Chimney

33

SCECO PP7

  • Fabrication and Installation of Cooling Tower

34

SCECO PP4

  • Fabrication and Installation of Overhead Crane 50 ton

35

SCECO PP2

  • Installation of 3,000 cfm Air Compressor including Air Receiver Tank Drayer, Oil Cooler and Air Line

36

Ministry of Defence, King Lhaled Military City

  • Supply and Installation of control System for chiller Water plant of KKMC

37

 

Electricity Coorporation, Mahad Al Dahab

  • Fabrication and Installation of Lube Oil Cooler
  • Rehabilitation of Lube Oil pipe line
  • Installation of Oil Sludge Pump and Repair Works

 

38

E. A. Juffali & Brothers

  • Rehabilitation and Installation of 250 HP Sewage Pumps
  • Fabrication and Installation of Treated Water Tank Power
  • Rehabilitation and Repair of Crawler Crane

39

SCECO PP4

  • Installation and Overhauling of 1600 cfm Air Compressor

40

SCECO PP7

  • Relocation of 4 MW Generator set (from Afif to Riyadh)
  • Overhauling of Generator and Air Cooler
  • Fabrication of cable tray Support Structure and Laying of Cable Trays and cables

41

SCECO PP5

  • Repair and Installation of Exhaust Diffuser and Stack Structure and related works

42

Southeren Province Cement Co., Bisha

  • Local fabrication and installation of Finish Mill
  • Rehabilitation of Deduster and structural Expansion

43

Southern Province Cement Co. Jizan

  • Installation of Swewage Tratment Plant
  • Installation of Hydro-Pneumatic Tank
  • Expansion of Automatic Air Pulsation Cleane

44

SCECO PP7

  • Repair of Air Cleaner Package for Genset

45

SCECO PP3

  • Structural Repair of Exhaust Stack and Deflectors
  • Repair of Exhaust Transition

46

SCECO PP3 Phase 1 & 2

  • Repair of Exhaust Stack and Transition
  • Rehabilitation of Intake Duct and Manifol

47

Ministry of Defense – Arar/Hadisha

  • Transfer of Diesel Genset from Arar to  Hadisha construction of New Power Plant Building in Arar
  • Re-installation of  Transferred Genset including connections of diesel and fuel pipelines and the associated electrical works

48

SCECO PP4

  • Overhauling and Repair of Overhead Crane

49

BPP2

  • Cleaning and Repair of Lube Oil Water Heat Exchanger (12 nos.)

50

PP7

  • Repair of Service Air Compressors (2 Units)

51

PP7

  • Repair of Lube Oil Heat Exchanger

52

Ministry of finance

  • Transfer of diesel Genset from Hail to Nasseriah Power Plant, Dismantling, Transfer, foundation, re-installation, Mechanical and Electrical connections

53

PP3 – Riyadh

  • Cleaning/maintenance of Radiators

54

PP7

  • Inspection of Main Atomizong Air Compressor

55

Yamamah Saudi Cement Company

  • Package #3 – Fuel Gas In-Plant Piping

56

PP7

  • Supply and Installation of New Air Circuit and Compressors

57

Qassim PP3

  • Repair of Exhaust system of Gas Turbines

58

PP5-Riyadh

  • Repair and Replacement of GT Insulation and Cladding for 5 Units

59

Qassim PP3

  •  
  • Repair of Stack Joint Seals

 

60

MASS PROJETS

  • Stringing of 132kV Double Circuit OHL from Madina North S/S to Khyber New S/S

61

Yamamha Saudi Cement Company

  • Package #5m Line 7 Fuel Gas Turbines

62

AL-FANAR

  • Emergency Shutdown Work of Tower Erection and Stringing of 380 KV Double Circuit Overhead Line towards S/S 9013

63

SWAYEH

  • Installation of Double Circuit Overhead Distribution Line, Earthing & Lightening Protection – Najran Water Transmission Project

64

PP9

  • Repair of GT #13 Damaged Parts

65

PP7

  • Joint Repair Exhaust Plenum
  • Unit# 13

66

 

Al-Fouzan National Guard and Military School campus

 

  • Complete Supply and Installation of Electrical system

67

Al Fouzan (Minstry of Health)

  • Riyadh Medical Complex
  • Complete Supply and Installation of Electrical and Mechanical System

68

SEC – Qassim Power Plant

  • Repair of hot Gas Exhaust for Unit #13 (Contract # 12002/49)

69

SEC-Layla Power Plant

  • Repair of Exhaust Leckage for GT’s 3 & 4

70

PP – 9 Riyadh

  • Repair of shrouds

71

PP – 9 Riyadh

  • Convention of Crude oil firing system of natural Gas

72

PP-7 Riyadh

  • Manufacturing of Blades

73

SEC-COA

  • SECPP9-Repair Damaged Parts-GT#13

74

SEC-PP7

  • Exhaust Plenum Repair of Gas Turbine frame 7001E for unit 11 in PP-7

75

Mawaris Co.

  • Replacement of expansion joint of Unit # 01, 08 & 15 at PP-9

76

MOF

  • Trouble shooting work at Nassaria PP

77

SECO-COA

  • Fix or replace the insulation for (2) Chimney in Layla power plant.

78

SECO-COA

  • Check and repair the Hot gas Exhaust for Unit #14 in Qassim Power Plant

79

SECO-COA

  • Replacement of Air Cooler of ABB Unit # 8 & 9 at PP3-Riyadh

80

SCECO-COA

  • Replacement of Air Cooled condenser shrouds at PP-9

81

 

Dallah Hospital

  • Electrical Work (Cable Laying from Transformer Room to SCECO Room)

82

Al-Etack Est.

  • Re-location of LPG & O2 tank in RMC

83

WETICO

  • Sewage Water Treatment Plant Power Supply

84

SEC-COA

  • Replacement of Buried Pipelines for PP-8

85

SCECO-SOA

  • Replacement of existing compressed air system of GIS operating mechanism in 132KV substation

86

SEC-COA

  • Replacement of Air Cooled Condenser Shrouds at PP-9

87

SEC-EOA

  • Rehabilitation of Oil Pressure Alarm system for Azizia-Thuqba underground cables.

88

Dallah Hospital

  • Electrical Work (Cable laying from Transformer room ro SCECO Room)

89

COMPACT

  • Replacement of Lamellah Seal, Expansion Joint & Actuators at PP9

90

COMPACT

  • Repair of Gt Plenum and replacement of Expansion Joint Liners at PP-9

91

SEC-EOA

  • Repairing of Inlet Air Cooling Coils for 6 GE Units at QCCP

92

SEC-EOA

  • Repairing of Inlet Air Cooling Coils for 6 GE Units at QCCP

93

SEC-PP  8

  • Modification of  Suldge & Diesel Oil  System

94

SWAYEH

  • 13.8 KV  Double Circuit  Over Head Line, Earthing , Lightining Protection &Installation.

95

QS PP3

  • Fuel Boilers  Repair Work At QCPP

96

SEC-COA

  • Repair of Expansion Joint at PP-9

97

AL MARAI

  • Rel . MV 13.8 KV Const’n Area B6A

98

Zamil

  • Modification of Chiller Cooling System

99

SEC PP9

 

  • Replacement of Air Cooled Condenser Shrouds of Section A1 and A2

100

SEC-SOA

Assir PP

  • Re-Insulation and repair of exhaust plenum
  • Supply & replacement of expansion joint
  • Replacement  of manhole gasket

101

SEC-SOA

Jazan PP

  •  Re-Insulation and repair of exhaust plenum
  • Replacement  of manhole gasket

102

SEC-SOA

Jazan pp

  • Re-Insulation and repair of exhaust plenum

103

SEC-SOA

Jazan PP

  • Re-Insulation and repair of exhaust plenum
  • Re-insulation & repair of silencer sheet
  • Replacement of manhole gasket

104

SEC-SOA

Najran PP

  • Re-Insulation and repair of exhaust plenum
  • Re-Insulation and repair of exhaust stack/chimney
  • Replacement of manhole gasket

105

SEC-SOA

Najran PP

  • Re-Insulation and repair of exhaust plenum
  • Supply & replacement of expansion joint

106

SEC-SOA

Najran PP

  • Supply and replacement of expansion joint

107

SEC-SOA

Bisha PP

  • Supply and replacement of expansion joint

108

SWAYEH

  • 13.8 OHL Earthing, Lighting Protection Installation

109

AL SHARQ

  • Repair Work of Plenum and Transition Place Area of GT 13

110

AL SHARQ

  • Repair of Silencer of GT # 13

111

AL SHARQ

  • Repair of Transition Piece A Part

112

MOJ

  • Improvement of A/C System in the Ministry New Building

113

SEC-COA

  • Modification of Genertor Cooling System for ABB Generators at PP-4

114

SASO

  • Mechanical & Fire Fighting Works

115

SEC-COA

  • Repalcement of Air Cooled Condenser Shrouds of Section A1 & B2

116

ZAMIL

  • Modification of Chiller Cooling System

117

KANOO

  • Replacement of 2 Unit Expansion Joint at PP-9

118

AL MARAI

  • Relocation of MV 13.8kV from Construction Area of B6A

119

SEC-COA

  • Reparing of Plate Heat Exchanger ( Evaporator ) for Westinghouse 1-5 Cooling System

120

ALMARAI

  • CPP2 Cold Store Expansion, B6A Capex., Supply & Install New Substation

121

ALMARAI

  • Supply & Installation of 2 MVA Substation for Accommodation Phase6 at CPP

122

ALMARAI

  • Supply & Installation of new CCP – EPT substation

123

ALMARAI

  • Supply and Installation of Labels for the MV Equipments & MV Substation Identification, CPP1A

124

ALMARAI

  • Supply & Installation of Labeling of LV Panel

125

ALMARAI

  • Supply and Install Cables to various Panels in BSA, CPP2     

126

ALMARAI

  • Laying PVC Sleeves around B6A S/S

127

Najran GT#6

  • Re-insulation, Repair and Replacement of Expansion Joint including Supply of Materials

128

Najran GT#6

  • Replacement of Expansion Joint

129

Najran Gt#5

  • Re-insulation and Repair of Expansion Joint including Supply of Materials

130

PP#9

  • Repair of Exhaust Sytem

131

PP#9

  • Re-insulation and repair of silencer baffles

132

PP#9

  • Repair of Exhaust system components

133

PP#7

  • Complete inspection and repair of exhaust sytem of GT#11

134

Juba PP

  • Repair of Exhaust Plenum

135

Qassim PP

  • Repair of expansion joint

136

Qassim PP

  • Repair of Exhaust System W/H Unit # 1

137

Hail PP

  • Inspect and repair parts of Chimney and repair Unit #  3

138

Hail PP

  • Inspect and repair parts of Chimney and repair Unit #  2

139

PP#9

  • Repair of Exhaust Plenum Expansion Joint GT # 6, 7, 8

140

PP # 9

  • Replace Expansion Joint at GT # 6
  • at Bypass exhaust stack expansion joint C

141

PP # 7

  • Inspect and repair exhaust system of GT # 16

142

Juba PP

  • Repair of exhaust system of Unit #  1

143

Juba PP

  • Repair of exhaust system of Unit #  2

144

Juba PP

  • Repair of exhaust system of Unit #  3

145

Juba PP

  • Repair of exhaust system of Unit #  6

146

Asser PP

  • Repair of Exhaust System Components for Asser Power Plant WH W501 D5

147

Najran PP

  • Supply and replacement of expansion joint at unit no. 8 – GE-FR-7

148

Najran PP

  • Repair Jobs on Unit Rate Basis at Najran Power Plant at Fait Unit No. 5 TG -20-B-7/8

149

Najran PP

  • Supply and replacement of Expansion Joint & Re-insulation and repair of Exhaust Plenum including supply of materials

150

SEC-COA

  • Replacement of Drinking Water

151

SEC-COA

  • PP#5 Tank # 11 & Tank # 12 Diesel Fuel Interconnection

152

Ministry of Finance

  • Relocation of HV Cables, 2 S/S and  Lighting  Pole between Hafr Al Bathain and Al Raghi

153

Almarai

  • Supply & Install MV & LV Cables for Refrigeration Upgrade,, CPP

154

Almarai

  • Repair of Piolt Cable CPP & Harad SCECO

155

Qassim PP

  • Repair of Exhaust system GT#7

156

Qassim PP

  • Painting Exhaust Chimney GT#7

157

Qassim PP

  • Repair of Exhaust System GT#3

158

Qassim PP

  • Repair of Expansion Joint GT#9

159

Qassim PP

  • Repair of Expansion Joint GT#6

160

Hail PP

  • Repair of Exhaust Chimney GT#5

161

Hail PP

  • Repair of Exhaust Chimney GT#4

162

PP # 9

  • Repair of Expansion Joint Unit#13

163

PP # 9

  • Repair of Expansion Joint GT#7

164

Juba PP

  • Repair of Exhaust System GT # 4

165

Asser PP

  • Repair of Exhaust System Components GT # 2

166

Tihama PP

  • Repair of Exhaust System Components GT#4

167

Tihama PP

  • Repair of Exhaust System Components GT#13

168

Almarai

  • Undergrounding of 33kv D.C OHL & PMT for Security Gate/Cradle Project

169

Almarai

  • MV and LV Cabling For 2 MVA RO Substation Electrical Equipment

170

Najaran

  • Repair, rehabilitation and replacement work on Exhaust Stacks GT # 2 Najran Power Plant

171

Almarai

  • Service Maintenance Job for LoLo Farm

172

Ministry of Finance

  • Relocation of HV Cables , 2 S/S and Lighting Pole Between Hafr al Bathain and Alraghi

173

SEC-COA

  • Connect the Tank #12 with Spare Line of the Tank #11 at PP-5

174

SEC-COA

  • Replacement of Drinking Water Pipeline at PP5

175

SEC-COA

  • Gas Turbine Exhuast System Repair and Rehabilitaion at Central Power Plant -WESTINGHOUSE

176

Almarai

  • Undergrounding of 33kv D.C OHL & PMT for Security Gate/Cradle Project

177

Almarai

  • Repair of Pilot Cable CPP & Harad SEC

178

SEC-SOA

  • Supply & Replacement of Expansion Joint of GT #8 at Najran PP

179

SEC-SOA

  • Repair of Exhuast System of Unit #23 at Jazan PP

180

Almarai

  • MV and LV Cabling For 2 MVA RO Substation Electrical Equipment

181

Almarai

  • Replacement of 33KV Dist.Transformer

182

SEC-SOA

  • Repair, rehabilitation and replacement work on Exhaust Stacks GT # 1 Aseer  Power Plant

183

SEC-SOA

  • Repair, rehabilitation and replacement work on Exhaust Stacks GT # 2 Najran Power Plant 

184

WETICO

  • Electrification Work at Jazan Immigration Housing

185

WETICO

  • Electrification Work at ICDOC Dammam

186

Almarai

  • Power Supply for New Building Accommodation Phase VII